BPRES News: Run Info and HV
Jan.4, 1999 :
HV for each PMT was finally optimized.
Starting from 1999 (31784 run), BPRES can be used for
the electron energy correction and other studies.
Jan.20, 1999 :
HV for each PMT was tuned according to the mean signal seen from DQM.
Jan.27, 1999 :
Fast Clear can be used for BPRES data.
Use O1TTY(IT1,IT2,IT3) to check trigger.
IF IT1=0 - this event was OK
IF IT1=1 - event was aborted (about 40% for 31944 run).
IF IT1=2 - test trigger.
Events with IT1=1 should be accepted for the BPRES analysis.
Feb.10, 1999 DQM was significantly modified.
Now all mean values are given in terms of units
closely related to pC, rather than PBTENE bank. Each unit
corresponds to 3 x pC. For example,
12 units in DQM corresponds to 4 pC seen from PMT.
Here a talk given at ZEUS Meeting (Feb.1999)
Feb.24, 1999 : Calibration. New HV setting was implemented using hadrons.
Starting from the run 32186, the
mean signal is expected to be 5 pC for each channel.
New HV setting
Feb.27, 1999 : Calibration. New HV setting was implemented using hadrons.
starting from the run 32206.
This calibration set is slightly tuned with respect to Feb.24.
If HV is below 800 and above 1200, it was set to nominal 955 for
1.25 gain.
New HV setting
March.03, 1999 :
Information on non-used and bad channels
Mar.15, 1999 : BPRES is included into TLT on-line (histos 20000 and 20001).
bpreszg.fpp written for ZGANA is
located in /canada/ntlt/tlt/1999/src/tltcalcode/
TLT histograms for BPRES can be found in /canada/ntlt/tlt/monitor/hist
March.19, 1999 : Calibration. New HV setting was implemented using hadrons.
starting from the run 32439.
This calibration set is slightly tuned with respect to Feb.27.
If HV is above 1200, it was set to 1200.
New HV setting
March.26, 1999 : Central DQM is finished for the BPRES.
README
May.21, 1999 : Access. Many PMT bases have been repaired.
(about 25 PMT basses)
Look at new HV status
July 26, 1999 : Calibration. New HV setting was implemented using hadrons.
starting from the run 33131. The gain for PMT is 1.25.
If HV is above 1200, it was set to 1200.
New HV setting
Aug. 12, 1999 :
Some problems after the access
Aug. 23, 1999 : Short access. The problems from the previous
access have been fixed. 4 channels should be good starting from the
run 033402
Aug.24, 1999 : Updated calibration.
New HV setting was implemented using hadrons.
starting from the run 33434. The gain for PMT is 1.25.
If HV is above 1200, it was set to 1200.
New HV setting
Aug.25, 1999 : Updated status on bad channels:
Bad channels
Sep.07, 1999 : Updated calibration.
New HV setting was implemented using hadrons.
starting from the run 33599.
New HV setting
Oct,06, 1999 : Updated calibration.
New HV setting was implemented using hadrons.
starting from the run 33818.
New HV setting
Dec,13, 1999 :
BPRES was turned off until January 14, 2000
Jan.10, 2000 :
Test of BPRES. No Y2K problem.
Updated status on bad channels:
Bad channels
March 6-8, 2000 :
Detector is open.
Due to water leak on BCAL module No3 during work on BCAL,
one channel
does not have read back (BPRE module N3, tile 9).
Heuijin replaced one channel : Now tile on module 4 tile 12
is set to spare channel 12 (before it was channel 51).
This swap is effective starting from physics run 35482.
April 4-5, 2000 : Access.
The last physics run is 35799.
HV PC was rebooted.
The current number of the channels with readback less than 700 V
is 16 (before the access: 21).
April 25, 2000 : The off-line DQM program was modified in
accordance with Steve's kumacs. Now there are two
sets of BPRE histograms
available: (1) and (2). The first set is created using profile
histograms generated from BPRE DQM ntuple. In this case the average
signals per channel are about 5 pC. This is consistent with the
other calibration
programs for which the 5pC charge is a reference signal.
The DQM program also creates a ntuple for each DQM run and copy it
into the public directory /chekanov/public/bpres/run_status/
with the previous DQM results.
April 30, 2000 : Cooling water problem in Ruckzack. Last run: 36119.
BPRES PC and CAMAC crate are off.
BPRES HV is off for 4 hours.
May 2, 2000 : Access. Last run is 36166. BPRES HV is off
May 18, 2000 : Access. Last run is 36340. BPRES HV is off
May 25, 2000 : calibration is finished for 00 data. BPRESTOOL is updated
May 27, 2000 : Emergency access. BPRES HV is off. Last run number is 26434
Jul. 12, 2000 : Access. BPRES HV is off. Last run number is 37091
Aug. 1, 2000 : Access. BPRES HV is off. Last run number is 37370
Mail to:
chekanov@mail.desy.de
© Copyright Sergei Chekanov
Updated: March, 2000